Saturday, July 11, 2009

Day 3

All of the demolition is done. We went to our contractor's shop, who by the way has as good as internet prices or better on stuff (http://www.tkbsupply.com/ over on Taraval in the SF sunset). We ordered:
  • Jason 527 tub
  • Toto Soiree bath fixtures
  • Toto Aquia II dual-flush toilet (we put this one in downstairs a year ago)
  • various other parts to make plumbing complete
We have already purchsed a Duravit sink with 2 faucets and Restoration HW cabinet for the corner. We have a cabinet maker making a stand for the sink rather than the very modern one you can purchase from Duravit.

2 new windows that are the same size are being built by a window shop and David will pick those up on Tuesday.

On Monday, they'll begin the plumbing work.